Keller installed 378 pcs of Ø600mm Lime Cement Columns within a small construction pit in Mjøndalen. The construction pit was made to establish a pump station to control future flood water situations.

Lime Cement Columns Wildenvey Park

The project

Nedre Eiker commune wanted to make a pump station in conjunction to Wildenveys park to better control future flood water situations from the nearby River in Mjøndalen. Keller was contracted to make a bottom slab of Lime Cement Columns in the construction pit during the execution phase. The main contractor was Kaare Mortensen Buskerud AS.

The challenge

In this project the biggest challenge was the lack of space in this small construction pit and the very soft ground. To be able to track the rig inside the pit we had to inject binder all the way to the top to stabilize the ground completely.

The solution

Keller established 378 pcs of Ø600 Lime Cement Columns with lengths of about 13 meter each. Due to the very soft soil in the construction pit, the columns had to go all the way up to the surface. Above the excavation level, a reduced amount of binder was used. The columns was tested with FKPS where a wing is penetrating the columns from above. The test showed a shear strength of well above the required shear strength of 100 kPa.

Project facts

Owner(s)

Nedre Eiker Kommune

Keller business unit(s)

Keller Grundläggning AB
Keller Geoteknikk AS

Main contractor(s)

Kaare Mortensen Buskerud AS

Engineer(s)

Project Manager Øystein Molandsveen